SOP BTA RMU-INS

SOP BTA RMU-INS
1

Periksa Bushing.
Pasang Copper.



2

ON semua Mechanism Z,T.

Periksa :
  Switching Blade MASUK PENUH.
  Pin Switching Blade Z,T : ada dan bengkok.
  Seragam ikatan Spring Switching Blade Z,T.
  Ikatan Main Busbar.
  Ikatan Internal Parts.

Pastikan jarak Rotating Arc – Fixed Contact Earth.
Moveable Cast Earth Z,T lancar.

OFF semua Mechanism Z,T.



3

EARTH ON semua Z,T Mechanism.
Pastikan Switching Blade MASUK PENUH.

Double Earthing Link OK.

OFF semua Z,T Mechanism.



4

Setting Mechanism Z,T OK.
4 pcs Nut diikat.
Drive Crank tiada freeplay.
Kedudukan Switching Blade di TENGAH.
Stopper (bawah) = 6 Conical Washer.
Laras Limiter Overshoot.



5
Pasang Kabel.


6

# BTA Z :

Tulis Tank No. dalam buku rekod BTA.

Key in Tank No. dalam KONFIGURASI RMU-INS.
( Test > Breaker Test Wizard > Pilih Tank No.Terakhir >
Next > Next > Taip Tank No. baru > Taip Feeder > Finish )

Key in Z-ˣ.
Pasang Rotary Transducer Set.
Calibrate Transducer : 2350 decimal.

Close Test.
Open Test.



7

# BTA T :

Key in T-ˣ.
Pasang Rotary Transducer Set.
Calibrate Transducer : 2350 decimal.

Close Test.
Open Test.



8

Tanggal Kabel.
Kemas Tools.
Air Blowing.
Lap habuk.
Pastikan tiada bolt, nut, bendasing, pelekat, tertinggal dalam Tank.



9

Mechanical Test.
Continuity Test.
Contact Resistance Test.
Insulation Resistance Test.



10
Masukkan Testing Results dalam sampul pada Tank.